Field note

Data Center Commissioning Levels: L1 to L5 for Drive Techs

Data center commissioning runs in levels, from factory test through the integrated systems test, and the drive tech has work at each of them, plus design and handover on some jobs. What each level includes is set by the job’s commissioning plan.

The commissioning firms’ pages explain the levels from the top. This note goes level by level through what the person setting up the fan and pump drives owns, and what tends to go wrong at each step.

Where the levels come from

ASHRAE describes a five level convention: L1 factory acceptance testing, L2 delivery and installation, L3 pre-functional checks, L4 functional performance testing of each system, and L5 integrated systems testing under real conditions and failure scenarios. The project’s commissioning plan defines the scope and acceptance criteria for each level, and the firms that run commissioning on these jobs split them their own way. JLL uses seven stages: Level 0 programming and design, Level 1 factory acceptance, Level 2 site acceptance testing, Level 3 start-up and pre-functional, Level 4 functional performance testing, Level 5 integrated systems testing, and Level 6 transition to operations. Firms such as IPS (Integrated Project Services) add a Level 1+ for testing modular electrical and mechanical rooms in the factory, including running some L3, L4 and L5 tests there before the module ships.

So a “Level 3” on one job may not be the same list of tasks as on the next one. The commissioning plan and the test scripts for the job are the source. When the plan says what the drive work at a level includes, do that. When it doesn’t, the sections below are a good place to start the conversation with the commissioning agent.

Level 0: design and submittals (on some jobs)

Not every job brings the drive tech in this early, but the decisions made here show up at every later level. If you get to review submittals, look at:

  • The voltage class and the supply. What feeds each drive, and whether any of it is on UPS. The notes on CRAH units and CDU pumps go through why that matters so much in a data center.
  • Bypass or redundancy. Whether the design counts on bypass contactors, a redundant drive transfer or a running spare. The note on VFD bypass vs N+1 runs the numbers.
  • Harmonics. Whether the harmonic study was run on generator power as well as utility power, and what drive options it calls for. IEEE 519 is evaluated at the site’s point of common coupling, as the note on IEEE 519 and drives explains. Any distortion limit the project sets for the generator bus is a separate, project specific number.
  • The sequences. What every drive is supposed to do on power loss, on power return, on loss of communication, and on a fire alarm. If the sequences don’t say, the L4 scripts won’t either.
  • The restart order. Whether the sequences stagger the restarts after a power loss, and where the delays live: in the drives, the unit controllers or the BMS. Dozens of fan and pump drives starting at once onto a generator that just came online is a big step load, and it can pull voltage and frequency down far enough to trip drives or the generator.
  • Long motor leads. Rooftop condensers, tower fans and remote pumps can put a lot of cable between the drive and the motor. The note on reflected wave and long motor leads covers when the motor needs a filter.

Level 1: factory acceptance

L1 is factory acceptance testing, checking that components meet the design before they ship. For drives that can mean a witness test at a packaged drive or air handler shop, or at the factory that builds the CDU or the modular plant. What to check:

  • The options. Low harmonic front end, communication card, bypass or redundant drive, enclosure, cable entries. Check them against the submittal, not the order.
  • The firmware version. Write it down. The restart, ride-through and comm loss behavior in the firmware manual belongs to a firmware revision, and every drive in a group should run the same one unless there is a reason.
  • The parameter file. If the drives ship programmed, get the file and check it against the approved sequence and the drive schedule: speed limits, ramps, restart and flying start, restart delays, comm loss action, and the communication address.
  • Redundant transfers. On a redundant drive package or a packaged unit with an ATS, watch the transfer happen at the factory. It is easier to fix there.

Level 2: delivery and installation

L2 checks that the equipment arrived and was installed right. Some plans, JLL’s among them, call this level site acceptance testing, and there it can include a witnessed functional check on top of the receiving inspection. Read the plan. The drive items are simple and easy to skip:

  • Damage and storage. Look for shipping damage, water, and dust in the enclosures. Find out where the drives sat between delivery and start-up, and whether that space was dry and heated.
  • The age of the drive. Drive DC bus capacitors do not like sitting unpowered. ABB’s capacitor reforming instructions say the capacitors need reforming if the drive has been non-operational for a year or more, and the same document shows how to read the build year and week from the serial number formats it covers. On a large job where equipment is bought early and stored, that clock can run out before start-up. How to reform depends on the model and how long it sat, and longer storage can call for a controlled procedure with an external circuit. Check the storage and reforming instruction for each model on the job, from each maker.
  • Spares. Log every spare drive, module and card that arrived, with its serial number and build date. The same reforming clock runs on the spares.
  • The installation. Clearances for cooling, the enclosure ambient, and that nothing blocks the drive’s airflow.
  • Construction dust. Drives that ran early to power temporary cooling during construction can have loaded heatsinks and filters. Clean them before L3.

Level 3: start-up and pre-functional

L3 is where the drive tech does the bulk of the hands-on work. These are pre-functional checks that each component is ready to run, which for a drive means the start-up itself. Work under the site’s lockout and arc flash rules the whole way through.

  1. Pre-energization checks. Terminations, torque, cable and shield termination, grounding, and the insulation resistance test of the motor and cable, done with the drive disconnected the way the drive maker says. The pre-startup checklist, the note on VFD cable and shield termination, and the note on megger minimums for 480 V motors cover them.
  2. Motor data and identification. Nameplate values in the drive, and the ID run if the drive and the load allow it. If a fan is still spinning when the drive is told to restart, flying start lets the drive pick it up without waiting for it to stop, and flying start depends on accurate motor data. The run command and the permissives still have to come back on their own.
  3. Rotation. On every fan and pump, using the approved bump procedure.
  4. Limits, ramps and restart delays. Minimum and maximum speed from the equipment and the sequence, ramps that suit the load, and any restart delay the sequence assigns to this drive.
  5. Communication. Addresses, baud rate or network settings, and every point read back at the BMS: speed, status, current, power, fault and mode. Reading a point back is not the same as proving a command, so also prove that each command the BMS sends, start, stop and speed, does what it should at the drive. The ACH580 BACnet MS/TP note goes through one brand’s setup.
  6. Lock it down. Once the start-up is done, lock or password protect the drive parameters where the drive allows it, so other trades and early operators cannot change settings before the IST.
  7. The start-up report. As-left parameters, firmware version, megger readings and anything that is not right yet.

The HVAC commissioning checklist covers the same ground for comfort cooling and carries over to a data center.

Level 4: functional performance testing

L4 tests the full functional performance of each system. Start with normal operation: start and stop, speed control, staging between units, and command and status at the BMS, all doing what the sequence says. Then move to the tests that prove the drives behave the way the sequence says when something goes wrong. Each one runs under the commissioning agent’s approved script, with the limits and abort criteria agreed first.

  • Comm loss. Pull the network on a running unit, or disable its communication the way the script calls for, and watch what it does. In a data center the expected answer is usually that cooling keeps running in its approved local or fallback mode. A drive that faults and stops on comm loss fails the test, unless the sequence calls for it, for example where a hardwired fallback or the unit controller takes over.
  • Power loss on one unit. Drop the supply to one running unit and watch the drive’s restart behavior, flying start, its restart delay and the run command come back. The CRAH note goes through that restart chain link by link.
  • Failover in an N+1 group. Trip one unit or pump and prove the others pick up the load inside their ratings. On a pump skid, trend flow and pressure through the swap.
  • The transfer the design relies on. Whatever was designed at L0 and witnessed at L1, bypass, redundant drive transfer or an ATS in a packaged unit, test it again here in place, on the real equipment and wiring.
  • Fire alarm and life safety. Prove the fire alarm sequence does what it is supposed to. On a clean agent room the fire sequence can call for mechanical systems to shut down when the agent releases, and that shutdown has to win over a comm loss setting that holds the last speed. Depending on the design, that shutdown can be a hardwired interlock into the drive or the unit, which is why it can override a network setting. Physically verify the interlock wiring and test it. On smoke control fans the sequence may call for fire mode instead. The note on fire mode and smoke control override covers how the drive brands handle it.
  • Alarms and points. Every drive fault and status alarm shows up at the BMS where the operators expect it.

Level 5: integrated systems testing

L5 runs integrated systems testing to confirm everything works together under real conditions and failure scenarios, with the IT load or load banks running. For the drive tech:

  • Utility to generator and back. A planned loss of normal power, switched by authorized electrical people under the IST script, with the site’s lockout and arc flash rules in force. Every fan, pump and chiller should come back as the sequence calls for, in the planned order. Then the retransfer back to utility, which on an open transition switch is a second interruption the drives have to survive.
  • UPS backed equipment. Where the design puts pumps or fans on UPS so they ride through the transfer instead of restarting, as some liquid cooled halls do, verify they did ride through as specified.
  • What to measure. Whether airflow, chilled water flow and coolant flow came back inside the site’s acceptance limits, and how long it took, not only whether the equipment restarted. Trend the generator’s voltage and frequency through the restarts to see the step loads, and check the restart delays as set.
  • Voltage on the generator bus. If the harmonic study or the project calls for it, read the voltage distortion on the generator bus with the drives running.
  • When a drive doesn’t come back. Capture the timestamps, the drive’s fault and event log, the state of the run command and permissives, and the unit controller status before resetting it or changing anything. Make changes through the commissioning lead, then rerun the affected step under the script. Be on site for the IST with the parameter files and a laptop, so that work can happen right away.

Level 6: handover to operations (on some jobs)

Not every job calls it Level 6, but the drives are not done until the operators can keep them running. Leave behind:

  • Parameter backups and firmware. A tested backup of every drive, stored where the operators can find it, and the firmware version of each. The note on VFD parameter backups covers the three kinds of backup and how each one fails.
  • A plan for the spares. A spare drive that has sat in a cage for years may need its capacitors reformed before it can go in, which costs time in the middle of an outage. Follow and log the maker’s storage and capacitor reforming procedure for each spare, and keep its parameter file and firmware matched to the running units.
  • Training. The operators should know what each drive is supposed to do on power loss and comm loss, how to read its faults, and when to call.

What tends to go wrong, and where to catch it

From the drive side, these are the problems that commissioning on a data center job is meant to catch, with the level that should catch each one:

  • Drives that restart fine but sit stopped after a power loss because the run command dropped out. Caught at L4 by the single unit power loss test, with the run command path traced at L3.
  • A unit controller or drive set for manual restart. Caught at L3 by checking the restart settings, and proven at L4.
  • All the drives restarting at once and step loading the generator. Caught at L0 by putting the restart order in the sequences, at L3 by setting the delays, and at L5 by trending generator voltage and frequency.
  • Firmware that differs across a group, so two identical drives behave differently on the same event. Caught at L1 and L3 by recording the firmware on every drive.
  • A comm loss setting that faults the drive on equipment that should keep cooling. Caught at L4 by the comm loss test.
  • Settings changed after start-up by another trade or an early operator. Caught at L3 by locking the parameters, and at L5 by comparing the as-found settings with the L3 report.
  • Spare drives that sat unpowered past the maker’s reforming limit. Caught at L2 by logging build dates, and at L6 by handing over a spares plan.
  • Parameter backups that were never tested and turn out not to restore. Caught at L6 by restoring one before handover.

Every one of these is cheap to fix at L3 or L4 and expensive to find during the IST, or after the site is live. A drive showing “running” is not proof that cooling recovered.

The ABB 580 start-up class at The Tolbert School covers ride-through, flying start, auto restart and comm loss setup on the ACH580. Other brands handle these differently, so check the manual for the drive on your job. The data center drives guide covers the rest of the drive work in a data center, and for tradespeople moving into this work, see data center training.

Frequently Asked Questions

What are the data center commissioning levels?

A staged way of proving a data center works before it goes live. ASHRAE describes five: L1 factory acceptance testing, L2 delivery and installation, L3 pre-functional checks, L4 functional performance testing of each system, and L5 integrated systems testing of everything together, including failure scenarios. Some commissioning firms, JLL among them, add a Level 0 for design and a Level 6 for the handover to operations.

Who defines the commissioning levels?

ASHRAE describes a five level convention, and the project's commissioning plan defines the scope and acceptance criteria for each level. Firms split and name the levels differently, so read the commissioning plan for the job you are on before you assume what a level includes.

What is an IST in a data center?

The integrated systems test, usually Level 5. All the systems run together under the approved test load and planned failures, such as a loss of utility power with the generators picking up the load. For a drive tech, the IST proves the cooling equipment responds to the outage and recovery as designed: the right units restart in the right order, and airflow and flow recover within the site's acceptance limits.

What does a VFD tech do during data center commissioning?

At L1, check the drive options, firmware and parameter files at the factory. At L2, check the drives that arrived and how they were stored. At L3, do the start-up: terminations, the insulation resistance (megger) test of the motor and cable with the drive disconnected the way the maker says, motor data, rotation, limits and communication points. At L4, prove normal operation, then comm loss, power loss and failover behavior on each system. At L5, support the integrated test and work through any drive that does not come back as designed.

Online start-up courses, filmed on real drives

One drive per course, filmed uncut with a clock on screen from first power to a saved backup. The install course is free, and the ABB ACS380 and ACS580 start-up course is open now.

See the online courses

Wayward Leaders® is a veteran-owned VFD training practice. We teach maintenance teams and plant electricians to install, commission, and troubleshoot variable frequency drives correctly.

Every class ends with a scored competency assessment. The plant gets a way to prove what each technician can do, not a roster of who sat in the room.

The instruction is field-trained. It is drawn from nearly 8,000 VFD, power, and motor documents and from more than 750 commissioned drives captured through personal field experience and data collection. Carl Lee Tolbert, PhD, CMRP, and ATD Master Trainer™, leads it. He has delivered more than 5,000 hours of VFD instruction across 30 years and trained 8,000 industrial professionals, from International Paper to the U.S. Navy.

The premise is simple: VFDs do not fail. Installations fail them. The curriculum is built backward from that.

Installation, commissioning, troubleshooting, and fault diagnosis guides are published openly at waywardleaders.com.